October 29, 2026
Where will you swim with a lifeguard on duty in Palm Beach next spring? For years the town has had two answers. As Palm Beach Civic Association columnist William Kelly reported in September, Midtown Beach and Phipps Ocean Park are the only two public beaches in town with lifeguard protection. Over the next few months, one of them comes back and the other is expected to close.
Phipps has been fenced off since May 2025 and reopens with a grand opening on Thursday, Nov. 19. Soon after, the town expects to close Midtown Municipal Beach for about 18 months to replace its seawall. If Midtown closes fully, Phipps will be the town's only public beach with lifeguards until about spring 2028.
In 1948 the family of Henry Phipps Jr. gave the town the 18-acre park, which runs from the ocean to the Intracoastal. WLRN reported that it has been called one of the most important philanthropic gifts ever made in Palm Beach County. The town still owns it. The Preservation Foundation of Palm Beach led the redesign and the fundraising, and the Foundation says it will pay for part of the park's maintenance in perpetuity. Burkhardt Construction holds the construction contract, which carries a $31 million guaranteed maximum price, and Raymond Jungles designed the landscape.
Phipps reopens in two stages. The tennis center and its parking reopened on Nov. 1, 2025, with two new pickleball courts added to meet demand. The Foundation has announced the grand opening of the rest of the park for Nov. 19 at 11 a.m. at 2201 South Ocean Boulevard. It is free and open to the public, and the Foundation asks guests to register on its event page.
The Foundation's plans for the park split into two parts:
According to WLRN, the project adds or relocates 80,000 native plants. The opening date moved more than once. The Civic Association reported a construction delay of nearly a year in 2025, and in April 2026 the Palm Beach Daily News reported that design changes had made a September finish less certain. The final weeks of the project ended up lining up with Midtown's closure.
The Midtown seawall runs 2,715 feet, from Royal Palm Way south to Gulfstream Road. It is close to 100 years old. Town Engineer Jake Hurley has said it is not failing, but engineering reports show it is near the end of its useful life. According to the Civic Association, it protects about $7 billion in private property, along with public streets and utility lines. The first cost forecast was about $20 million.
Council members first asked whether the beach could stay partly open while the work moved along in sections. According to the Palm Beach Daily News, town staff said a phased approach could sharply raise costs and double the length of the project. Crews would have to set up again and again, the town would buy materials later at less certain prices, and it would need temporary beach entrances and restrooms that require regular upkeep. Hurley told the council a single full closure would be faster, use less space and disrupt neighbors less.
Sea turtles set the timing. Nesting season runs from March 1 to Halloween, and staff want to start during the winter so construction overlaps only one nesting season. The sand added to Midtown Beach in the recent renourishment will be used to build barriers on the ocean side that keep turtles from nesting inside the work zone. The 2026 nesting season closed on Oct. 31, so the window the town is aiming for is open now.
During construction, barriers will cover the eastern parking spaces on South Ocean Boulevard. The screening on the street side will be printed with an ocean scene. Hurley has said two-way traffic will stay open on South Ocean Boulevard throughout the work.
| Date | Phipps Ocean Park | Midtown Beach |
|---|---|---|
| Nov. 1, 2025 | Tennis center and parking reopen | Open |
| Oct. 31, 2026 | Construction finishing | Turtle nesting season ends |
| Nov. 19, 2026 | Grand opening at 11 a.m. | Open |
| As early as November 2026 | Open | Murray Logan expected to submit its guaranteed maximum price and detailed schedule |
| December 2026 to early 2027 | Open | Seawall work and closure expected to begin |
| About spring 2028 | Open | Forecast finish if work starts this winter |
The start date has been reported two ways. In September, the Civic Association reported a December start. In October, the Daily News said early 2027. Both reports put the length at about 18 months. The design-builder, Murray Logan Construction of West Palm Beach, is expected to submit its guaranteed maximum price, drawings and a detailed schedule as early as November. That schedule should give the first firm closure date.
At the council's Sept. 8 meeting, Council member Lew Crampton, a South End resident, said Midtown beachgoers would likely head to the beaches east of Sunrise Avenue and to Phipps. The Civic Association quoted his warning:
"Those folks are going to go south, and you are going to have a potential overload there."
Hurley described the effect around Midtown differently, according to the same Civic Association report. "Throughout the project, we should see better traffic," he told the council. "We're not going to have individuals coming from off-island to park at the beach."
Both can happen at once. With fewer beach visitors, traffic around Royal Palm Way and South Ocean Boulevard could ease, while Phipps takes on many of the swimmers Midtown used to serve. The new beach pavilions, showers and remodeled lifeguard stand will open just as Phipps gets its busiest stretch in years. If you use Phipps now for a quiet walk on the Dune Crest Path or a picnic by the mangroves, expect more company on the beach side this winter and spring.
Several pieces are still open. A full closure was the option staff favored in the Daily News report, and the council had earlier said it wanted more discussion before deciding between partial and full closure. The town set a public outreach meeting for Oct. 29 at Town Hall, 360 S. County Road, to cover the closure and traffic. November's schedule from Murray Logan will show whether that meeting changed the plan.
What comes after the seawall is also still in design. The town plans to rebuild the linear park on the east side of South Ocean Boulevard, from Gulfstream Road to Royal Palm Way, with wider sidewalks, more green space and pocket parks east of each intersection. That plan still needs review and approval from the Architectural Commission. In August, some council members objected to the proposed sidewalk layout from Royal Palm Way south to Chilean Avenue, which would turn the walkway nearest the seawall into a serpentine path. The park work is planned to start after the wall is finished, so the Midtown that reopens will look different from the one closing.
Until then, the island's lifeguarded public beach will be at 2201 South Ocean Boulevard. For more on how the island's season is changing, see our look at the rooms reshaping Palm Beach evenings and our Palm Beach neighborhood page.
If you own near South Ocean Boulevard and are wondering how a long construction period and a busier South End fit your own plans, Leila Kallop would be glad to talk it through over a quiet conversation. Request a private consultation.